Nike AirMI – Manufacturing Facility Expansion

Murphy Company successfully installed all mechanical and plumbing systems for the multi-million expansion of Nike AirMI’s manufacturing facility in St. Charles, Missouri. This extensive project was completed without disrupting the 24/7 operation of the international footwear manufacturer.

The facility’s new water-cooled chiller plant consists of three 600-ton HVAC chillers and two 600-ton process chillers, eight cooling tower cells, and new pumping systems.

This design-assist project involves three separate manufacturing building additions with new utilities and HVAC service for each addition. Murphy upgraded the existing building with all-new HVAC systems including six new 160-ton chilled water air-handling units and two 25,000 cfm dedicated outdoor air units.

Murphy Company’s careful planning and execution ensured that the facility’s operations continued uninterrupted while significantly enhancing its mechanical and plumbing capabilities.

Owner Nike AirMI
Building Type Manufacturing Retrofit
Project Size $16,000,000
Contract Type GMP, Design-Assist
Completion Date 2020
Project Duration 33 Months

Murphy Team

William Conaway (Project Manager)
Conrad Philipp (Project Executive)
Mike Werdes (Precon Manager)
Robert Grossmann (Lead Estimator)
Brian Vaughan (Engineer)
Steven Harting (Engineer)
Luke Toedebusch (Plumbing Foreman)
Jeff Welch (Piping Foreman)
Vic Ashley (Sheet Metal Foreman)

Project Team

General Contractor: Alberici Corporation
Engineer: McClure Engineering
Architect: Fox Architects
Electrical: Guarantee Electric

Scope of Work

HVAC
Piping
Plumbing
Sheet Metal