Denver Health – Bernard F. Gipson Eastside Family Health Center

The Bernard F. Gipson Eastside Family Health Center was in need of significant upgrades to the heating/cooling system and plumbing fixtures throughout the three-story building. The scope of work included the demolition of two existing duct risers and two existing AHUs, installation of two new AHUs, associated risers, 25 VAVs, and new plumbing fixtures throughout the building totaling about 80 fixtures.

The family health center had to remain open and occupied during the installation, which created a challenge for Murphy to overcome from a planning standpoint. The building was split up into 18 different working areas throughout the 8-month duration to keep the health center operational. Our team also flushed and cleaned their hydronic system (heating and cooling) which will increase the longevity of the piping and equipment served by the heating and cooling system. Ultimately, Murphy provided a renovated lobby and examination rooms to support the center’s dental, OB/GYN, physical therapy, pediatrics, and walk-in clinic offerings.

Owner Denver Health
Building Type Renovation
Project Size $1,100,000
Contract Type Lump Sum
Completion Date 2019
Project Duration 8 Months

Murphy Team

Project Manager: Chris Hornberger
Piping Foreman: Paul Combest
Plumbing Foreman: Lez Rice
Sheet Metal Foreman: Steven Romero

Project Team

General Contractor: Howell Construction
Engineer: Cator Ruma
Architect: TreanorHL
Electrical: IME

Scope of Work

HVAC
Piping
Plumbing
Sheet Metal