Kindeva – Lap Scope

Murphy Company was contracted by Kindeva to retrofit a 5,000-square-foot second-floor laboratory space with new lab gases, lab hoods, and supporting utilities. The project scope included extending existing stainless-steel lab gas lines to specified user locations, installing a new exhaust system for six lab hoods, and providing utilities for a new parts washer.

Midway through the project, mold was discovered in the lab, causing a three-month delay while remediation took place. Despite this setback, Murphy maintained a consistent on-site presence and shifted manpower to other available scopes of work. This approach allowed progress to continue wherever possible and kept the overall retrofit moving forward, even amid a volatile schedule.

The project required a high degree of adaptability to changing scope. Frequent modifications and owner requests were addressed by assigning Murphy’s designer to take on the role of on-site project engineer, ensuring clear communication and precise execution in real time. The project also demanded specialized expertise, and Murphy was able to leverage the same management and field teams from a recent high-purity installation. Their knowledge of “out-of-the-ordinary” lab systems resulted in a smooth, efficient installation process.

Safety was a top priority throughout the project. The early detection of mold prompted Murphy’s safety team to implement additional protocols, including the use of respirators, to allow essential pre-remediation work to be completed safely. At the same time, Murphy’s team stepped into a collaborative leadership role. With the construction manager being less experienced, our crews provided critical direction and influence over both project scope and schedule, contributing greatly to the project’s success.

Through proactive planning, technical expertise, and strong leadership, Murphy delivered a high-quality, fully functional lab space for Kindeva—despite significant challenges and delays.

Owner Kindeva
Building Type Retrofit
Project Size $585,000
Contract Type Lump Sum
Completion Date 2024
Project Duration 9 Months

Murphy Team

Project Executive: Lloyd Jarden
Project Manager: Drew Retzer
Preconstruction: Mike Werdes
Piping Foreman: Dan Wieczorek, Nick Carrol, Darren Johnson

Project Team

General Contractor: Kindeva
Engineer: Murphy Company
Architect: CRB Architects-Engineers PC

Scope of Work

Piping