dji 0484

Nike AirMI – Manufacturing Facility Compressor Upgrade

Murphy Company performed a critical air compressor upgrade for Nike AirMI. Our team installed four new water-cooled air compressors to replace the manufacturing facility’s existing original compressors. The project included close coordination for shutdowns to tie in the new system to the existing compressed air system. Murphy performed this work as the prime contractor managing the electrical and controls subcontractors.

Owner Nike IHM, Inc.
Building Type Retrofit
Project Size $768,400
Contract Type Lump Sum
Completion Date 2022
Project Duration 5 Months

Murphy Team

Operations Manager: Nick Kniesche
Project Manager: Brian Vaughan
Piping Foreman: Seth Redd

Project Team

General Contractor: Murphy Company

Scope of Work

Piping
Process Piping