Corden Pharma – Plant 3 – Phase 3 – Moderna Tank Farm Expansion

The Phase III Moderna Expansion project was completed in April 2022 in Boulder, Colorado, at Corden Pharma. Corden Pharma has been one of Murphy Company’s longest tenured customers in the Colorado Market. The project consisted of expanding the tank farm for Plant 3 to increase capacity of production for their customers. This was also the third phase of this project on the plant since 2020. The main challenges our project team ran into was completing the project within the tight schedule and budget. In the 6 months, we installed eight new tanks within Plant 3 that included process and utility piping to each tank. It was a well coordinated effort to communicate with all trades to complete the work safely. Throughout the course of all the project phases we had zero recordables.

Owner Corden Pharma
Building Type New Construction
Project Size $4,500,000
Contract Type GMP
Completion Date 2022
Project Duration 6 Months

Murphy Team

Operations Manager: Brad Andrews
Project Manager: Justin Rheinheimer
Superintendent: Greg Pflipsen
Piping Foreman: James Connell

Project Team

Prime: Murphy Company
Engineer: APECS

Scope of Work

Piping