image

Schriever Space Air Force Base

Murphy Company was hired by Aleute Global Solutions, LLC to assist in a mechanical room upgrade at Schriever Space Air Force Base (formally Schriever Air Force Base). This project was located on the east side of Colorado Springs and the scope of work consisted of replacing the existing condensate pump receivers, hot water pumps, and heat exchangers. Due to scheduling and site access, we utilized our CAD department and piping prefabrication facilities. The hot water pumps were mounted on prefabricated skids along with pump accessories and piping. All equipment and piping arrived on-site and ready for installation. Murphy Company was also the prime contractor and managed the completion of the temperature controls, insulation, and commissioning.

Owner Aleute Global Solutions, LLC
Building Type Renovation
Project Size $500,000
Contract Type Lump Sum
Completion Date 2010
Project Duration 4 Months

Murphy Team

Project Manager: John Portscheller
Piping Foreman: Terry Mitchell

Project Team

General Contractor: Murphy Company
Engineer: RMH
Electrical: Berwick Electric

Scope of Work

HVAC
Piping