thermo fisher piping 2

ThermoFisher Scientific – B2 Expansion Phase 2

Murphy Company was contracted to provide the Phase 2 Expansion of B2 at the ThermoFisher Scientific site in St. Louis, MO. The project involves a 28,000-square-foot footprint addition to the existing Building 2, which is a continuation of the Phase 1 Expansion completed in 2019. This will expand the Building 2 footprint to the east to include two new processing suites – Suites 10 and 11, including production clean rooms, support clean rooms, mechanical and utility areas, new dock areas, and other supporting functions. The utility infrastructure expansion includes chillers, cooling towers, WFI generation, storage, and distribution, clean steam generation, and compressed air generation.

Murphy developed an initial cost opinion by taking the design criteria provided by McGrath and CRB which included general arrangement drawings, point of use sketches, and material specifications, by gap-filling the missing information by gaining an understanding of the intent of the system design, the project factors, and the decisions that were influencing the design. During the design-assist process, Murphy provided constructibility reviews and real-time cost estimating to help complete the design documents and took over the Virtual Design effort at 60% CD for final routing and coordination of all utilities, ultimately generating the 100% CDs.

Murphy led the BIM construction coordination process, which started with the underground utility systems. Murphy started construction immediately after coordination signoff in October of 2022 with the installation of the underground systems. Murphy was able to maintain this underground construction schedule by identifying an issue with the materials specified for the process waste system due to supply chain issues and working with CRB to determine an acceptable alternate material and manufacturer.

This project includes eight months of preconstruction and eight months of construction. It is on a fast-track schedule with above-ground installation starting in May of 2022 and will be substantially completed in March of 2023.

Owner ThermoFisher Scientific
Building Type Pharmaceutical Processing
Project Size $30,000,000
Contract Type GMP, Design-Assist
Completion Date 2023
Project Duration 22 Months

Murphy Team

John Koebbe: Senior Project Manager
Drew Retzer: Project Manager
Justine Schaper: Project Engineer
Dan Wieczorek: Pipefitter Superintendent
Dale Hirons: Sheet Metal Superintendent
Justin Manley: Plumbing Superintendent
Mike Werdes: Preconstruction
Dylan Blake: BIM
Kevin Suiter: Estimating
Brian Vaughan: Engineering
Steve Bruening: Engineering

Project Team

General Contractor: McGrath & Associates
Engineer/Architect: CRB
Controls: Siemens and Trane

Scope of Work

HVAC
Piping
Plumbing
Sheet Metal
Process Piping