The Anheuser-Busch Filler Beer Recovery project was bid and executed based off of one line P&ID drawings and included procurement and installation of 5000’ of schedule 5 stainless steel piping and associated fittings. Our team also completed the fabrication of stainless steel hangers and skid manifold supports to accommodate piping and owner-furnished Tuchenhagen valves, flow meters, and other miscellaneous process instrumentation. The installation occurred in fully functional filler and packaging areas with high pedestrian traffic and fully operational processes. We pushed to complete this project within the three-month schedule without disturbances to Anheuser-Busch production.
Anheuser-Busch – Filler Beer Recovery
Owner Anheuser-Busch
Building Type Existing Building Fitout
Project Size $800,000
Contract Type Lump Sum
Completion Date 2017
Project Duration 3 Months
Murphy Team
Project Manager: Trevor Sundheim
Plumbing Foreman: Aaron Ferster
Project Team
General Contractor: Murphy Company
Engineer: BW Design Group
Electrical: CES
Scope of Work
Process Piping